- Anticipate investments. The grid must be prepared for future electrification needs, rather than starting to act only when demand already exists.
- Increase grid capacity wherever an increase in demand associated with industry, electric mobility, HVAC, self-consumption, or new economic activity is expected.
- Modernize and digitize the grid to make it more flexible, efficient, and resilient, and to be able to integrate more electricity consumption and renewable generation.
- Streamline planning and authorizations for new infrastructure so that grid development timelines can keep pace with those of new industrial and economic projects.
- Have a remuneration and regulatory framework that allows for future-oriented investment, anticipating the needs that the energy transition will entail.
- Plan the grid with tomorrow’s economy in mind. Industrial electrification, new data centers, or electric mobility require available capacity when projects decide to set up.
- In short, understand the electricity grid as an infrastructure that enables decarbonization and competitiveness, and not as a brake on the process.
The electrical grid is key for the decarbonization and competitiveness of the Catalan industry
Decarbonization does not consist only of generating renewable energy. Catalonia needs a resilient grid to continue being competitive. Endesa defends its role as an industrial and country infrastructure.
Accelerating decarbonization in Catalonia requires coordinating energy planning with industrial and territorial needs, streamlining permits, and ensuring that transport and distribution networks grow at the same pace. A stable regulatory framework that facilitates investments, strengthens the supply of materials, and trains specialized professionals is also necessary. Delays in infrastructure, which can reach ten or eleven years, are one of the main obstacles to advancing electrification.
The grid is no longer just an energy infrastructure, as explained by Endesa. It is an industrial and national infrastructure. The availability of electrical capacity, connection lead times, and supply quality increasingly influence decisions regarding investment, expansion, or the location of factories, data centers, housing, and new economic activities. It is necessary to have connection capacity, but also to rely on a competitive electricity price. Industry settles or grows where it finds available power and a credible connection schedule and, therefore, electrical capacity is a factor of territorial competitiveness.
Anticipating demand
For decades, network investments have been executed primarily based on needs that were already confirmed. The current transformation demands a change in this approach to get ahead of future demand. When a new factory, an electrification process, a data center, or a large urban development is announced, it is too late to start planning all the necessary infrastructure. It is necessary for networks to be developed in advance, based on industrial, urban, and territorial forecasts shared by administrations, companies, and operators.
Royal Decree 640/2026 speaks about anticipatory investments and establishes their percentage. However, anticipating investments does not mean oversizing the electricity grid, but rather planning it according to future electrification needs. Expanding its capacity allows for connecting more industries, companies, and new consumption, favors decarbonization, and distributes system costs among a larger demand. Therefore, investing more in the grid should not necessarily mean a higher cost for citizens.
As Endesa warns, every megawatt that cannot be connected can mean an industrial expansion that is delayed, an investment that seeks another location, or a decarbonization project that continues to depend on fossil fuels. And it is not enough for the grid to be flexible because the limitation is significant. Flexibility is only a complementary solution to infrastructure reinforcement, not an alternative.
Managing a network with more self-consumption, batteries, electric vehicles, distributed generation, heat pumps, electrified industry, and data centers requires much higher digital capabilities. It is necessary to monitor medium and low-voltage networks in real time, strengthen control centers, incorporate new calculation systems, and have algorithms that allow executing instructions on flexible installations. It is also necessary to increase protection against risks linked to cybersecurity.
AI also needs a network
The development of artificial intelligence is increasing the demand associated with data centers. These facilities require large volumes of electricity, with high supply continuity and predictable connection deadlines. In 2024, data centers requested 19.3 GW of access capacity in Spain, slightly above the 18.6 GW requested by the industry.
It is obvious that AI needs electricity, but above all it needs a planned, digitized network with firm capacity. Industrial, digital, and energy policies can no longer be designed separately. The issue should not be posed solely as a competition between artificial intelligence and industry for limited capacity, they point out from the company. The challenge is to expand and modernize the network, organize requests according to the actual maturity of the projects, and prevent speculative requests from blocking capacity needed by initiatives ready to be executed.
The new state framework introduces mechanisms such as the capacity reservation payment, the linking of permits to actual activity, and the expiration of projects that do not progress. It also establishes priorities for housing, public services, expansions of existing consumption, and strategic industrial projects.
Having a connection is essential, but not sufficient. For a company to replace gas or other fuels with electricity, the operation must also be economically viable. Decarbonizing is not just being able to electrify, but that electrifying is a competitive industrial decision.
Catalonia has industry, knowledge, technological capacity, and renewable potential to advance in decarbonization. But it needs an electrical grid that supports this transformation. Investing in grids is not just energy policy: it is industrial, competitiveness, and territorial cohesion policy.
- In October 2026, 90% of distribution nodes appear to be saturated
- In 2025, nearly 40 GW of access and connection were requested from the State, of which only 12% (4.5 GW) has been granted.
- For its part, 66% (25 GW) could not be accommodated, while the remaining 22% (8.5 GW) is still being processed. (Source AELEC)