The high speed between Barcelona and Madrid will not recover normality until next week
The disruptions to the schedules will last until Renfe and Adif can remove the train that caught fire on Monday afternoon and the infrastructure is repaired
-
CAT -
CAST
BarcelonaNormal high-speed rail service between Barcelona and Madrid will not be restored until the beginning of next week. This was announced this Wednesday by the new spokesperson for Adif in Catalonia, Antonio Carmona, who explained that the work to remove the train affected by Monday's fire is complex and can only be carried out at night, because it is incompatible with train traffic on the adjacent track.
The incident occurred on Monday near Ricla, in Aragon, when the tail locomotive of an AVE train that had departed from Madrid bound for Figueres caught fire. The 283 passengers traveling on the train had to be evacuated, although no injuries were reported. Traffic resumed a few hours later but only partially—on a single track—and remains restricted on a stretch of about 25 kilometers in Aragon.
Thus, in this section, trains are running on a single track, a limitation that can extend journeys by between 10 and 15 minutes, as detailed by Carmona. In the last few hours, Adif has been able to increase the maximum permitted speed from 80 to 160 km/h, but the line's capacity remains constrained until the burnt train is removed.
The tasks to remove the train require dismantling and removing the part of the locomotive affected by the flames with the help of a large crane. Once this operation is completed, Adif technicians will have to inspect and repair the damaged infrastructure elements, including the overhead lines, before restoring traffic on both tracks.
Meanwhile, Renfe, Iryo, and Ouigo have announced that they are adapting their services to the capacity limitations, with schedule changes and disruptions on some routes. According to Carmona, Adif and the operators are maintaining coordination to manage the service while the restrictions last. The causes of the fire remain under investigation.
Changes at Adif
Carmona's appearance is the first one he has made as a spokesperson for Adif since his change of company was made public. The historic spokesperson for Renfe (who for a few months also held the position of director of Rodalies) has left the train operator to now take charge of the management of the tracks, from the Adif side. The position of director of Rodalies has fallen since last summer to Òscar Playà, who is the new managing director of the joint company (between the State and the Generalitat) Rodalies de Catalunya.
Among his new duties, in addition to being spokesperson, Carmona will coordinate actions with the Generalitat, the city councils, and the rest of the administrations and involved agents, as stated in the competition rules for the position. He will have to develop and monitor the network's work plan, report periodically on the progress of the projects, and prepare an annual monitoring report. Among the tasks of his new role described in the call for applications are also analyzing demand and detecting new planning needs.